The Pennsylvania Department of Transportation (PennDOT) announced that construction on its High-Speed Interchange between I-80 and I-99 will begin on Wednesday, September 4. This project will enhance traffic safety by providing a direct connection between the two highways, making it unnecessary to travel along Route 26 to access them, relieving traffic congestion, and realigning service for local traffic.
Starting Wednesday, the contractor will begin shoulder reconstruction and widening on I-80 eastbound and westbound between mile markers 158 and 163. It will reduce traffic to one lane between 6:00 PM and 6:00 AM to mitigate traffic impacts while completing this work. PennDOT anticipates shoulder reconstruction and widening to continue for approximately two months. All work is weather-dependent.
Crews will also be within the project limits during daylight hours to complete excavation work off the roadway. PennDOT does not expect this to cause additional traffic impacts but urges drivers to exercise caution in all work zones, obey posted speed limits, and always buckle up.
Overall work on this project includes building the interchange, ten bridges, four retaining walls, five box culverts, seven sign structures, and three changeable message boards. It also includes constructing new and rebuilding existing roadways and ramps, drainage improvements, installing Intelligent Transportation Devices, guide rail and highway lighting, pavement marking, stream improvements, and miscellaneous construction. Work will continue through the next six construction seasons, ending in 2030.
The high-speed interchange is the next phase of a three-phase project. The first involved the construction of the local access interchange at mile marker 163, which provided direct access between Route 26 and I-80 for local traffic. Construction on that phase occurred over three construction seasons between 2020 and 2022. The contract value was $52 million. That phase benefited from a $35 million federal Infrastructure for Rebuilding American (INFRA) grant.
The remaining phase will reconstruct and widen Route 26 to maintain and support the State roadway network. It will feature 11-foot travel lanes and 4-foot shoulders. That project bid on Thursday, August 22, with Glenn O. Hawbaker, Inc. of State College, PA, named the apparent low bidder at $8.6 million. Construction on that phase will begin in the 2026 construction season.
Completing all three phases will support the regional freight economy and improve the reliability of roadway travel throughout the region.
What’s happening on Interstate 80 RIGHT NOW! I-80 Real-time traffic information for cities along I-80. Maps show updates on road construction, traffic accidents, travel delays and the latest traffic speeds. Traffic cameras show congestion at a glance. Visit I-80 Traffic.
The I-80 Exit Guide is the Internet’s largest and most complete website dedicated to Interstate 80 travelers. Find detailed exit service listings… lodging, camping, food, gas and more for every exit from Maine to Florida!
On the road? Why not take us with you. The I-80 Exit Guide is mobile-friendly and totally FREE. No App Required.
Traveling another route? Visit our growing family of exit guides: I-4 Exit Guide, I-5 Exit Guide, I-10 Exit Guide, I-75 Exit Guide, I-80 Exit Guide and I-95 Exit Guide. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit along the way!