With recent warm temperatures, the Wyoming Department of Transportation (WYDOT) and contract crews have begun mobilizing crews for I-80 construction in Sweetwater County.
On Wednesday, April 1, WYDOT and contract crews will be switching I-80 traffic to head-to-head in the westbound lanes from mile marker 141 to 155 near Patrick Draw for pavement rehabilitation work.
The work will include milling and paving and the completion date is set for October 31, 2026. The eastbound Bitter Creek rest area will be closed and not be accessible for the duration of the work.
All work is weather dependent and subject to change.
What’s the traffic like on Interstate 80 RIGHT NOW? I-80 Real-time traffic reports for cities along I-80. Maps show updates on road construction, traffic accidents, travel delays and the latest traffic speeds. Traffic cameras show congestion at a glance. Visit I-80 Traffic.
The I-80 Exit Guide is the Internet’s largest and most complete website dedicated to Interstate 80 travelers. Find detailed exit service listings… lodging, camping, food, gas and more for every exit from New Jersey to California!
On the road? Why not take us with you. The I-80 Exit Guide is mobile-friendly and totally FREE. No App Required.
Traveling another route? Visit our growing family of exit guides: I-4 Exit Guide, I-5 Exit Guide, I-10 Exit Guide, I-75 Exit Guide, I-80 Exit Guide and I-95 Exit Guide. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit along the way!